Views: 0 Author: Site Editor Publish Time: 2022-05-10 Origin: Site
The electric chain hoist manufacturer reminds you: the newly purchased electric chain hoist needs to do no-load test and load test, because the test before use can effectively see whether the electric chain hoist is in a normal state, so the electric chain hoist is in a normal state. The operation test of the electric hoist is a very important process.
The electric chain hoist that is newly installed or installed after dismantling and inspection should be tested with no-load first. After several times, if there is no abnormality, the next step can be carried out.
Before normal use, a static load test of 100 mm from the ground at 125% of the rated load should be carried out for 10 minutes, and check whether it is normal. This is what we call an overload test.
The dynamic load test is to perform repeated lifting and left-right movement tests at the rated load weight. After the test, check whether the mechanical transmission part, the electrical part and the connection part are normal and reliable.
The pre-use operation test of the electric chain hoist can effectively detect the health status of the electric chain hoist, which is convenient to detect abnormalities in time, and it is a very important part to be aware of it.